This article breaks down how to move unit using a Site Task.
Starting from your Park Administrator Role Centre, click on Site Task in the Main List Area
You will be taken to the list of Site Tasks.
Site Tasks are generated automatically when new Deals are processed, but should you need to create a manual one , then click on +New in the top ribbon
A new line has been created for you to complete.
The Site Task Number will generate automatically, so click into the blank field for Type Code first
Select MOVE from the list of options
Click into the Unit Number field & select the Unit you are planning to move.
You will see that the From Park Code and From Plot Number fields have both pulled through the data for the Unit you have selected.
Next select where the Unit is going to move to
Click into the field for Park Code
If you're moving the Unit to a different one of your Parks, this is where you will enter the new Park Code
Select your Park Code
Next, click on the ellipsis button for Plot Number to choose the new Plot for your Unit
Select your new Plot from the list. Make sure you are selecting a Plot which doesn't already have a Unit on it
Click OK to confirm your choice
Now you can decide the Due Date for this Site Task to be completed.
Click into the Due Date field to open the date picker Select a Due Date from the calendar
New Site Tasks will be given the Planned Status.
For the work to start, you will need to change this to Confirmed
Click on the Due Date & enter the date the unit needs to move
The status field will now move to Confirmed
Tip: It is recommended that Site Tasks are checked regularly in order to keep on top of them. We would suggest checking the list at least once a week, so that you can ensure new tasks are set to Confirmed and completed tasks are set to Completed
Click on the back button to close Site Tasks when finished